Woodlawn-King Alleys Sewer Repair Project Update: October 3, 2017

2017-10-04 23:01:53| PortlandOnline

The nighttime construction on Alberta Street has been delayed and is not scheduled to begin within the next few weeks. Most of the Cured-in-Place-Pipe repairs in the neighborhood have been completed.

Tags: october project update repair

 

Woodlawn-King Alleys Sewer Repair Project Update: September 12, 2017

2017-09-12 19:19:14| PortlandOnline

Environmental Services is preparing to begin construction on the Woodlawn-King Streets Sewer Repair Project. The project will repair or replace over 16,000 feet (over 3 miles) of public sewer pipes in your neighborhood that are on average 90 years old and in deteriorating condition.

Tags: september project update repair

 
 

Woodlawn-King Alleys Sewer Repair Project Update: August 31, 2017

2017-09-01 17:25:29| PortlandOnline

Crews have been installing sewer clean-outs throughout the neighborhood, and will continue to do so. In the coming weeks, sewer lines in the alleys will be repaired using cured-in-place-pipe lining.

Tags: august project update repair

 

Woodlawn-King Alleys Sewer Repair Project Update: August 18, 2017

2017-08-22 17:23:46| PortlandOnline

Crews will focus on installing cleanouts and restoring concrete in several alleys. Cured-in-place pipe-lining will resume at multiple locations starting August 28.

Tags: august project update repair

 

Woodlawn-King Alleys Sewer Repair Project Update: July 27, 2017

2017-08-01 18:03:55| PortlandOnline

Crews are moving through the project area repairing pubic sewers in the alleys through Cured-in-Place Pipe-Lining (CIPP). Cleanout installations followed by concrete restoration will continue in multiple locations.

Tags: july project update repair

 