SE Hawthorne-Salmon Area Green Street and Sewer Project Update: January 22, 2015
2016-01-25 23:23:26| PortlandOnline
Next week crews will continue to video inspect sewer lines on SE Hawthorne Boulevard. Final paving of trenches currently patched with temporary asphalt has been re-scheduled for the week of February 1.
Tags: area
january
street
project
SE Hawthorne-Salmon Area Green Street and Sewer Project Update: January 15, 2015
2016-01-19 17:12:35| PortlandOnline
Next Monday and Tuesday, crews are scheduled to video inspect sewer lines on SE Hawthorne Boulevard to prepare for sewer construction tentatively scheduled for late February or early March.
Tags: area
january
street
project
SE Hawthorne-Salmon Area Green Street and Sewer Project Update: January 8, 2015
2016-01-11 21:31:29| PortlandOnline
Environmental Services continues construction on the SE Hawthorne-Salmon Area Green Street and Sewer Project. The project includes installing 23 green street planters, planting 100 street trees, and repairing or replacing over 10,000 feet of public sewer pipe. These improvements will extend the service life of our sewer system and protect public health, property and the environment by reducing the possibility of sewage releases into streets, homes and businesses.
Tags: area
january
street
project
SE Hawthorne-Salmon Area Green Street and Sewer Project Update: December 23, 2015
2015-12-29 00:08:00| PortlandOnline
Environmental Services continues construction on the SE Hawthorne-Salmon Area Green Street and Sewer Project. The project includes installing 23 green street planters, planting 100 street trees, and repairing or replacing over 10,000 feet of public sewer pipe. These improvements will extend the service life of our sewer system and protect public health, property and the environment by reducing the possibility of sewage releases into streets, homes and businesses.
Tags: area
december
street
project
SE Hawthorne-Salmon Area Green Street and Sewer Project Update: October 22, 2015
2015-10-24 01:19:46| PortlandOnline
Environmental Services will begin construction in early November 2015 on the SE Hawthorne-Salmon Area Green Street and Sewer Project which will include installing 23 green street planters, planting 100 street trees, and repairing or replacing over 10,000 feet of public sewer pipe. These improvements will extend the service life of our sewer system and protect public health, property and the environment by reducing the possibility of sewage releases into streets, homes and businesses.
Tags: area
october
street
project