Firm building Muskrat Falls transmission lines files for bankruptcy protection
2015-11-27 21:17:54| Energy - Topix.net
Abengoa was awarded a $200-million contract to build 400 kilometres of transmission lines on the west coast of Newfoundland and in Nova Scotia. NSP Maritime Inc., a subsidiary of Emera Inc. , says they have contractual protections in place to ensure the work continues.
Tags: building
files
lines
protection
Muskrat Falls hydroelectric project in Labrador over budget and delayed
2015-09-30 11:12:11| Energy - Topix.net
ST. JOHN'S, N.L. - The cost of building the Muskrat Falls hydroelectric project has grown by almost 10 per cent to a total of $7.65 billion since June 2014. Nalcor Energy also says the date for when power is first expected to be generated from the project in Labrador has been delayed until 2018.
Tags: project
budget
falls
delayed
Muskrat Falls hydroelectric project on time and on budget: Nalcor Energy
2014-12-01 15:59:01| Energy - Topix.net
ST. JOHN'S, N.L. - The Muskrat Falls hyroelectric project remains on time and the price tag is still pegged at almost $7 billion by Nalcor Energy. Nalcor CEO Ed Martin says the project is still on track to start producing power by the end of 2017 and the cost of the project in Labrador remains unchanged from updated estimates released this summer.
Tags: time
project
energy
budget
More audits for Muskrat Falls project in Labrador after costs rise
2014-07-31 18:55:46| Energy - Topix.net
ST. JOHN'S, N.L. - A provincial oversight committee for the $8.5-billion Muskrat Falls hydro project in Labrador has asked for more audits to monitor spending.
Tags: project
costs
rise
falls
Cost of Muskrat Falls project jumps by $800 million for Nalcor Energy
2014-06-26 21:21:46| Energy - Topix.net
ST. JOHN'S, N.L. - The cost of building the Muskrat Falls hydroelectric project in Labrador has risen by nearly $800 million for Nalcor Energy with the price tag now forecast at just under $7 billion.
Tags: project
cost
million
energy