Home green street
 

Keywords :   


Tag: green street

Clinton Green Street and Sewer Construction Update: January 30, 2015

2015-02-03 17:47:16| PortlandOnline

As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.

Tags: january street update green

 

Clinton Green Street and Sewer Construction Update: January 22, 2015

2015-01-24 01:38:20| PortlandOnline

As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.

Tags: january street update green

 
 

Clinton Green Street and Sewer Construction Update: January 13, 2015

2015-01-14 20:53:03| PortlandOnline

As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.

Tags: january street update green

 

Clinton Green Street and Sewer Construction Update: December 22, 2014

2014-12-22 23:50:02| PortlandOnline

As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.

Tags: december street update green

 

Clinton Green Street and Sewer Construction Update: December 15, 2014

2014-12-16 17:24:31| PortlandOnline

As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.

Tags: december street update green

 

Sites : [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] next »