Piedmont Sewer Repair Project Update: November 22, 2016
2016-11-23 01:43:03| PortlandOnline
No work is scheduled Thursday, November 24, through Sunday, November 27. Below is the estimated construction schedule for the next two weeks. Please be aware that this schedule is subject to change due to a variety of factors, including conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials. To view a project map, go to www.portlandoregon.gov/bes/article/550313.
Tags: november
project
update
repair
NW District Sewer Replacement Project Construction Update: November 18, 2016 Night Work to Continue
2016-11-19 01:42:02| PortlandOnline
The Portland Noise Control Office granted Environmental Services a noise variance for overnight construction at specified locations (see map) for up to five months on this project. Night work hours are 8:00 p.m. to 5:30 a.m. Sunday through Thursday. If you have questions or concerns during night work hours, you can call the City of Portland on-site hotline at 503-823-6290. You can also contact the Portland Noise Control Office at 503-823-7350 or noise@portlandoregon.gov.
Tabor Sewer Repair Project Construction Update: November 16, 2016
2016-11-17 01:13:25| PortlandOnline
The maps posted at www.portlandoregon.gov/bes/tabor show the anticipated construction schedule through December and look ahead through December 2. Work in each area will take a few weeks to complete and there will be periods of inactivity between construction phases.
Tags: november
project
update
construction
Lower Powell Green Street and Sewer Repair Project Update: November 9, 2016
2016-11-10 23:02:03| PortlandOnline
As part of the Tabor to River Program, Environmental Services will soon complete construction on the Lower Powell Green Street and Sewer Project. The work includes installing 22 green street planters, planting 11 trees, and repairing or replacing 4,508 feet of public sewer pipe. These improvements will extend the service life of our sewer system and protect public health, property and the environment by reducing the possibility of sewage releases into streets, homes and businesses.
Tags: november
street
project
lower
Piedmont Sewer Repair Project Update: November 4, 2016
2016-11-08 00:53:13| PortlandOnline
Night work on North Lombard Street between North Kerby and Vancouver avenues is scheduled to begin next Monday, November 7, through Friday, November 18
Tags: november
project
update
repair