Tabor Sewer Repair Project Construction Update: August 10, 2017

2017-08-11 01:14:47| PortlandOnline

Construction is continuing on Environmental Services Tabor Sewer Repair Project. This project in its entirety is scheduled to be completed by fall of 2017.

Tags: august project update construction

 

SW Yamhill-Morrison Sewer Repair Project: Construction continues

2017-08-09 18:22:52| PortlandOnline

Environmental Services is continuing work to repair public sewer pipes in SW Yamhill and SW Morrison Streets in downtown Portland. Repairs to the 100 to 140-year-old sewer pipes will protect the public and the environment by reducing the possibility of sewage releases to buildings and streets.

Tags: project construction repair continues

 
 

Powell Sewer Repair Project Construction Update: July 28, 2017

2017-08-01 18:25:22| PortlandOnline

Construction continues on Environmental Services SE Powell Sewer Repair Project. This project in its entirety is scheduled to be completed in the fall of 2017.

Tags: july project update construction

 

Southeast Interceptor Sewer Repair Project: Construction begins at SE 16th & Pershing

2017-07-18 18:20:14| PortlandOnline

Environmental Services is beginning construction on a project in inner southeast Portland to repair the deep, large-diameter Southeast Interceptor sewer line that is deteriorating due to age. The repairs will extend the life of the sewer and protect public health, water quality, and the environment.

Tags: project construction repair begins

 

Sewer construction to close SW Terwilliger Blvd south of Castleridge starting December 5

2016-11-28 21:44:55| PortlandOnline

November 28, 2016

Tags: december close south construction

 